London Office Fit Out in 7 Weeks
How long does it take to complete an office fit out in London? We were able to complete all of this in a 7 week programme within budget and to the full satisfaction of our client.Saffron Hill EC1 Momentum Transport Consultancy Case Study 2020
Initial Interiors have recently completed the fit out of Momentum Transport Consultancy new offices in Saffron Hill EC1, working to the clients design and improving the design where possible to give better value for money and a office space that works better for the clients business.The scope of works was quite large to consist of:
- Short project timeline at 7 weeks to fit out completion
- Contracting team worked out of office hours and weekends
- One fully furnished boardroom
- Two meeting rooms with noise reducing glazed walls
- Two private phone booths in the office space
- An extended large breakout area with a catering kitchen and a tea point
- New showers installed with sustainability in mind
- Overall spec was to create an office space suitable for a workforce of up to 90 people
Glass Office Partitions for Boardroom and Meeting Rooms
The boardroom and two meeting rooms were constructed in a line, running parallel to the existing windows, with high glazed fronts to allow natural light from the windows to spread to the open plan area. With the new door frames and doors painted to match the existing window frames of the office.
The filming of the glazed sections incorporated the names of the rooms used in their existing offices to allow continuity between their new and existing offices. Particular attention was paid to the partitions dividing the boardroom and meeting rooms to stop sound transference between them, with each room having a TV screen mounted on one wall to allow for video conferencing and a visual aid for presentations.